PROJECT: Gold's Gym – Northridge

PROJECT STATS

    • Industry
    • Commercial
    • Location
    • Northridge, CA

Project Overview

Gold’s Gym – Northridge

Scope of Work

  • Sprinkler coverage will be provided below new suspended and hard lid ceilings only as shown for Construction type II-B on provided plans and specifications.
  • Existing upright coverage shall remain the same with no change. Heads will be spaced light hazard for “A-3”, “B” and “S” occupancies.
  • Fire Sprinkler Heads installed under T-Bar shall be center of tile respectively.
  • Fire sprinklers in new scope of work to be new quick response per NFPA 13 2019.
  • All piping to be added and/or relocated are to meet local and NFPA 13 2016 standards and the City of Los Angeles Building and Safety.
  • Design-Build Engineering will be provided with our services.
  • Work shall include all materials, labor, plans, shop drawings, plan submittal, rough and final inspections.
All ()
Commercial ()
Residential / Hospitality ()
Industrial ()
Education ()