PROJECT STATS
- Industry
- Commercial
- Location
- Santa Barbara, CA
Project Overview
ORANGE THEORY – Santa Barbara
Scope of Work
- Demolition/removal of existing drops in hard lids to be removed.
- Sprinkler coverage will be provided throughout 623 unit, in new hallway and along new demising wallsas shown on provided plans and specifications.
- Heads will be spaced ordinary hazard for “M” occupancies.
- Fire Sprinkler Heads installed under T-Bar shall be center of tile respectively.
- Fire sprinklers in new scope of work to be new quick response per NFPA 13 2019.
- All piping to be added and/or relocated are to meet local and NFPA 13 2016 standards and the City of Santa Barbara Fire Department.
- Work shall include all materials, labor, plans, shop drawings, plan submittal, rough and final inspections.
All ()
Commercial ()
Residential / Hospitality ()
Industrial ()