Project Overview

ORANGE THEORY – Santa Barbara

Scope of Work

  • Demolition/removal of existing drops in hard lids to be removed. 
  • Sprinkler coverage will be provided throughout 623 unit, in new hallway and along new demising wallsas shown on provided plans and specifications.  
  • Heads will be spaced ordinary hazard for “M” occupancies.  
  • Fire Sprinkler Heads installed under T-Bar shall be center of tile respectively.  
  • Fire sprinklers in new scope of work to be new quick response per NFPA 13 2019. 
  • All piping to be added and/or relocated are to meet local and NFPA 13 2016 standards and the City of Santa Barbara Fire Department. 
  • Work shall include all materials, labor, plans, shop drawings, plan submittal, rough and final inspections. 